July 2024

Inhabitr

Terrazul

Miami, FL

Terrazul is a 931 Class A student development serving the FIU campus in Miami, FL. This community offers an impressive range of amenities, including three indoor fitness areas, an outdoor pool and sunset deck, a sky lounge, a conference room, ample study spaces, a club room, a game room, barbecue grills, and a running track pathway.

Launching a student‑housing community in a dense Miami submarket, Terrazul needed hundreds of units furnished, staged, and handed over on a compressed summer timeline. Shipping delays threatened the schedule, multiple vendors were moving simultaneously on site, and the on‑site team required clear daily visibility without disruptions to building operations.

931

Apartment Units

30 Days

Project Duration

10,000+

Total Items

Project Metrics

Metric

Details

Details

Project Specs:

The Solution

Our Strategy

The Turn Company deployed a phased, floor‑stack installation program designed to protect schedule, quality, and resident experience. Crews coordinated receiving, assembly per manufacturer specs, in‑unit placement, and rolling debris removal, sequencing upper floors first to keep the project moving while upstream deliveries caught up. Daily quality checks with on‑site management created rapid feedback loops, while clean‑site standards and defined paths‑of‑travel kept common areas open and safe. Commercially, the team maintained actuals‑based invoicing and documented any delivery‑driven scope extensions in writing to preserve transparency.

Screenshot 2024 01 03 174848
Screenshot 2024 01 03 174928

Our Results

The Turn Company deployed a phased, floor‑stack installation program designed to protect schedule, quality, and resident experience. Crews coordinated receiving, assembly per manufacturer specs, in‑unit placement, and rolling debris removal, sequencing upper floors first to keep the project moving while upstream deliveries caught up. Daily quality checks with on‑site management created rapid feedback loops, while clean‑site standards and defined paths‑of‑travel kept common areas open and safe. Commercially, the team maintained actuals‑based invoicing and documented any delivery‑driven scope extensions in writing to preserve transparency.

Pre-Install Readiness

Verified labor quantity estimates ahead of time to avoid delays.

Quality Control

On-spot inspection and daily sign-offs.

Phased Execution

Floor-by-floor cadence with zone leads.

Team Management

Challenges overcome by strong process management.

Close-Out

Completed final walkthroughs and delivered consolidated documentation.

Outcomes & Results

931

Apartment Units

30 Days

Project Duration

10,000+

Total Items

Key Success Factors

Testimonial

Ready to Transform Your Property?

Let's build your schedule backward from move-in while you focus on residents.