Flooring Project
WaHu Apartments | Minneapolis, MN
- Replaced approximately 49,000 sqft of common-area flooring across floors 2–11, including hallways, elevator lobbies and study rooms
- Installed staggered glue-down LVP, herringbone feature areas and more than 14,000′ of cove base in two phases

Furniture Install
Straits Row | Chicago, IL
- 6,600+ FF&E items
- 132 units in a multifamily new development
- Multi-phase install
- 18 person crew scaled appropriately for each phase

Seasonal Turn
Westmar | Atlanta, GA
- Turnover included 689 beds/ baths & 261 common areas.
- Services provided: painting and cleaning
- Completed in twenty days

Furniture Install
The Standard | Minneapolis, MN
- 9,121 FF&E items
- 1,021 beds in 385 student housing units
- 26 day install window
- 22 person crew averaging 350 items per day

Furniture Install
Terrazul | Miami, FL
- 10,000+ FF&E Items
- 1201 Bedrooms in 931 student housing units
- 30 active work days
- 40 shipping containers of goods

Renovation
The Curtis | Denver, CO
- Renovated 15 uniquely themed guest suites
- Scope included flooring, paint, wallpaper, plumbing, lighting, FF&E, and extraction.
- Completed in two phases over six weeks.

Parking Lot
Hilton Garden Inn | Denver, CO
- Managed the restoration of 27,000 sqft of parking area
- Work performed: patching, sealing, crack repair, re-pouring curbs and painting
- Completed in three stages over the course of 11 days

Furniture Install
SoL | Tempe, AZ
- 1,082 items extracted and installed
- 108 bedrooms in 27 student housing units
- Executed in tandem with seasonal turn operations
- Completed in six days

Seasonal Turn
Denton Student Apt | Denton, TX
- Turnover included 601 beds/ baths & 425 common areas.
- Services provided: painting, cleaning, make-ready
- Completed in eight days

Seasonal Turn
Axton | Madison, WI
- Turnover included 342 beds/ baths & 173 common areas
- Services provided: painting, cleaning, make-ready
- Completed in 14 days

Paint Project
The Lotus | Boulder, CO
- Painted 22,000 sqft of common area walls (two tone), 2,700′ of trim and 80 doors
- Completed in nine days with zero disruption to students

LED Install
Clear Creek Village | Flagstaff, AZ
- Installed a combined 6,300 LED bulbs and fixtures
- Project included interior and exterior replacement while navigating the cities “dark sky” regulations.

ESG Installation
Tradition at 777 | Baton Rouge, LA
- Installed centrally networked humidity monitors in common areas of all property apartments
- Facilitated planning, procurement, installation, and training